Honeywell wt6500 Video Gaming Accessories User Manual


 
25
Commissioning
SMARTBOX™ Controller for HONEYWELL™ Wind Turbine WT6500 Owner’s Manual - Rev14
6. Select the battery Amp-hour rating for ONE battery by using the arrow keys. Press
ENTERwhennished.
Display Description Optimal
ENTER BATTERY AHr 100 Set the battery amp-hour rating
for ONE battery
Enter 140 for 100Ahr
batteries
7. Select the number of battery banks in parallel by using the arrow keys. Press ENTER
whennished.
Display Description Optimal
ENTER BATTERY BANKS 1 Set the number of battery banks Enter 3 for one bank of
2-12V batteries
8. At this point the batteries are all set up. Now you will proceed to setting up the turbine
and checking its components for operation. Turbine setup requires two people: one
located at the turbine and one located at the system Smart Box.
9. Step 10 is for testing the turbine. Turn on the turbine disconnect.
10. If the wind is not causing the turbine wheel to spin, gently spin the wheel by hand to
determine if the system Smart Box is detecting a voltage level.
Display Description
TURBINE INPUT OK Shows if a turbine voltage was found.
11. Step 12 is for testing the AC grid connection. Turn on the AC disconnect from the grid
input.
12. Check the LCD screen and make sure the AC voltage is OK. Press ENTER to
continue.
Display Description
AC Grid 120V OK??
Checks the AC voltage. Press ENTER
to skip this step if this is a non-grid-tie
connection.
13. Step 14 is for testing the AC load connection.Turn on the AC disconnect to the load.
Turn on all items on the sub panel load to make sure that the turbine inverter can
handle the load.
14. The system commission process is now complete. Press ENTER to start the turbine. If
required, this process can be restarted via the technician’s menu.
Display Description
COMMISSION COMPLETE Press ENTER to start the turbine.